pics : BICEP : 0312 pole trip : primary and interface prep

Up


Preparations of the new pieces to mount on DASI, including the interface plate and primary.

( Click once for medium sized image. Click again for full size. )
100_0095
100_0095

All crates were delivered to our site (primary shown here) within two days of our arrival.
100_0097
100_0097

The platform was erected by Dave Carlson et al. on Saturday morning, Dec 13.
100_0099
100_0099

The bolts holding the primary in its crate were found to have loosened in shipping; one fell out.
100_0100
100_0100

100_0101
100_0101

100_0102
100_0102

100_0103
100_0103

100_0128
100_0128

The staging platform.
100_0131
100_0131

100_0136
100_0136

Deformed high spots on the mirror mounting flange were obvious around the bolt holes.
100_0137
100_0137

These were removed by hand, by countersinking and scraping.
100_0139
100_0139

100_0140
100_0140

100_0141
100_0141

A ding in the side of the flange also raised a high spot, which was scraped down.
100_0142
100_0142

100_0143
100_0143

100_0182
100_0182

1-wire serial temperature sensors were installed on the primary back.
100_0185
100_0185

100_0186
100_0186

100_0232
100_0232

The sensors were fitted with clips to attach to the primary ribs.
100_0272
100_0272

100_0273
100_0273

100_0252
100_0252

Making the spreader triangle out of 2" steel angle.
100_0253
100_0253

100_0268
100_0268

This triangle will be saved by Jack Corbin/Bill Johnson if possible so we can use it next year.
100_0270
100_0270

The guard ring was adjusted to fit pretty well.